Mallard Pass Solar Farm

Mallard Pass Solar Farm is one of the UK's most ambitious renewable energy projects, combining large-scale solar energy generation with a strong commitment to sustainable land use and community benefit.

Project Timeline:

Spring 2022

Consultation and Development

Winter 2022

DCO Application submitted

July 2024

Development Consent granted

XXX

Quinbrook and PEP purchase the DCO permission to deliver the project

October 2025

Establishment of Community Liaison Group

Now

2025-2026

Pre-construction

est. Q1 2027

Construction begins, anticipated to take 2-3 years

40 years

Project operational lifespan



How will my community benefit?

A Community Benefit Fund worth £96,000 per year throughout the operational life of the project.

An additional one-off construction fund of £200,000 for local communities.

Independent administration of funding arrangements to ensure transparency and accountability.

Use of local contractors and supply chains wherever possible and creating and sustaining new jobs throughout construction and the project’s operational lifespan.

About us

Mallard Pass Solar Farm is one of the UK’s most ambitious green infrastructure projects combining large-scale solar energy generation with a strong commitment to sustainable land use and community benefit. Mallard Pass represents the future of responsible energy, driving sustainable growth for Lincolnshire, Rutland and the United Kingdom.

PEP (Private Energy Partners) are an affiliate of Quinbrook Infrastructure Partners, with its team having proven expertise in the delivery of energy projects for more than four decades. They have contracted Fichtner Consulting Engineers as the project manager for the delivery of Mallard Pass.

Sign up to receive project updates